This week’s progress will include:
- Erecting our structural steel in the lobby
- Infills on east and west walls will be completed
- Ceiling tile will be dropped in all 30 classrooms
- Leadership area will be textured, painted and will have an acoustical grid completed
- Our audio/visual contractor will begin installing displays on their Diversitrack in the classrooms
- Ceramic tile in bathrooms will be completed
- We will have all hollow metal exterior frames installed
- We will begin to glaze the leadership hollow metal frames
- We will start up the remaining fan coils and tie them into the chiller