This week’s progress will include:

  • Furnishing and punching out all 30 classrooms 
  • Installing lights in the exterior corridor
  • We will have flooring, grid, and lights installed in the lobby area
  • The floor will be passed off by the Fire Alarm inspector allowing the space to be used by the public
  • The millwork throughout the floor will be installed
  • All flooring will be complete
  • The 1st floor will be ready for teachers and staff
  • We will begin the final cleaning for the rest of the floor