This week’s progress will include:
- Furnishing and punching out all 30 classrooms
- Installing lights in the exterior corridor
- We will have flooring, grid, and lights installed in the lobby area
- The floor will be passed off by the Fire Alarm inspector allowing the space to be used by the public
- The millwork throughout the floor will be installed
- All flooring will be complete
- The 1st floor will be ready for teachers and staff
- We will begin the final cleaning for the rest of the floor