Whiteboards and Water Chillers

This week we begin to erect structural steel in the lobby and media center and will continue to abate the exterior corridors. As we continue to finalize the north center classrooms, we will begin working on the drop ceiling tile and install whiteboards in the north and northeast classrooms.

The temporary water chiller will be used to chill water lines from the exterior of the building to the second floor. On the exterior, we are busy at work setting posts on the North field for the chain link fence to be installed.